BID RESULTS

D & G Backhoe Inc. Low Bidder on 2018 Capital Improvement - 32nd St. SE Water Main Replacement Project in WA

D & G Backhoe Inc. is the apparent low bidder on the Snohomish County - Public Utility District's 2018 Capital Improvement - 32nd St. SE Water Main Replacement Project solicitation, with a low bid of $1,502,168.80 USD. Bids were opened on September 12, 2018

The contract will be for Install with appurtenances approx 40 LF of 6" DI class 52 water main, approx 8,360 LF of 8" DI water main class 52, approx 144 LF of 12" DI class 52 Water main and approx 90 LF of 16" HDPE water main. The project also includes installation of 136 water services and surface restoration.

Additional bidders include:
B & L Utilities, Inc: $1,538,881.87 USD
SRV Construction: $1,604,855.50 USD
Laser Underground & Earthworks, Inc.: $1,935,999.11 USD

For additional information on this project and vastly more, visit www.napc.pro