BID RESULTS

Bontke Brothers Construction Company Low Bidder on Kirby Lake Dam, Fort Phantom Hill Dam, and Lake Abilene Dam Miscellaneous Repairs in TX

Bontke Brothers Construction Company is the apparent low bidder on the Abilene, City of's Kirby Lake Dam, Fort Phantom Hill Dam, and Lake Abilene Dam Miscellaneous Repairs solicitation, with a low bid of $3,464,900.00 USD. Bids were opened on September 11, 2018

The contract will be for Work includes dam miscellaneous repairs.

Additional bidders include:
Welch Excavation and Utility Company, Inc.: $4,669,123.66 USD