BID RESULTS

Visual Systems Inc Low Bidder on 2018 Sanitary Sewer Reconstruction Phase 8 (Project #468-85347) in KS

Visual Systems Inc is the apparent low bidder on the Wichita, City of Engineering Dept.'s 2018 Sanitary Sewer Reconstruction Phase 8 (Project #468-85347) solicitation, with a low bid of $149,405.20 USD. Bids were opened on October 12, 2018

The contract will be for Works include approx 1,522 LF of 8" PVC sanitary sewer; 9 EA of 4' sanitary sewer manhole; 17 LF of concrete pvement removal and replacement; 41 EA of 4" service re connections; and 20 SY of erosion control.

Additional bidders include:
Amigo Excavation & Plumbing LLC: $153,533.22 USD
Dondlinger & Sons Construction Co., Inc.: $173,492.00 USD
Wichita Excavation: $211,230.00 USD

For additional information on this project and vastly more, visit www.napc.pro