Cen-Cal Construction Low Bidder on Annual Contract for Canal Liner Repair in CA

Cen-Cal Construction is the apparent low bidder on the Bakersfield Purchasing Division's Annual Contract for Canal Liner Repair solicitation, with a low bid of $371,500.00 USD. Bids were opened on October 11, 2018

The contract will be for For providing a annual contract for canal liner repair. The work consists of the removal and installation of canal concrete side and bottom panels. Specs: 20,000 SF construct side panel as per city standards average size 12'x13-1/2'x4"; 50 CY slurry sand in-place; 50 CY rock fill in-place; 110 CY back fill.

Additional bidders include:
Jim Alfter Cement Contractor: $399,070.00 USD