K R Swerdfeger Construction Low Bidder on IFB - FY 2018 Small Main Rehab Remove and Replace/Lining Project in CO

K R Swerdfeger Construction is the apparent low bidder on the Pueblo Purchasing Dept.'s IFB - FY 2018 Small Main Rehab Remove and Replace/Lining Project solicitation, with a low bid of $1,453,698.00 USD. Bids were opened on November 15, 2018

The contract will be for Work includes approx 244 LF remove and replace 8" PVC; 990 SF remove and replace 7" reinforced concrete; 603 LF of 8" PVC; 1 EA galvanized water service; 2 EA new manhole; 453 LF remove and replace asphalt patch; 52 VF epoxy coat; 26 TN alley rotomill; 377 LF of 8" CIPP liner; 12.9 VF epoxy coat 48" manholes. See outside link.

Alternate bid values are: $532,011.00 USD