BID RESULTS

Coyote Ridge Construction, LLC Low Bidder on RFP - CR31/14.5 Waterline Extension Project in CO

Coyote Ridge Construction, LLC is the apparent low bidder on the Fort Lupton, City of's RFP - CR31/14.5 Waterline Extension Project solicitation, with a low bid of $365,962.50 USD. Bids were opened on November 19, 2018

The contract will be for Work includes approx 5,500 LF of 12" PVC waterline; 1 EA new 2" water service tap with saddle; 80 LF of 2" copper water service line; 2 EA of 2" curb stop valve; 2,650 LF seeding; 325 SY of 6" patch back HMA. See outside link.

Additional bidders include:
Nre Excavating Inc: $384,496.00 USD
Roberts Excavation Corporation : $424,019.15 USD
Northern Colorado Constructors Inc.: $490,365.00 USD